St Margaret’s Residential – Magdalen Rd, Exeter – Grenadier Estates Ltd. & Skinner Construction Ltd.
Project Overview
St Margaret’s, a former girls’ school has undergone extensive works as part of a residential conversion into luxury apartments. Phase one of the project involved the complete renovation of the site’s most prominent listed buildings, Baring Lodge, Weststall House and Wynalton House.
Client: Grenadier Estates
Contractor: Skinner Construction
Contract length: 20 weeks
Challenges
Faced with the problem of covering some of Exeter’s grandest listed buildings, Ledger Scaffolding needed to deliver complete free-standing scaffolding all enclosed with temporary roofing over multi-levelled roof heights.
Solution
Guided by technical drawings, Scaffolding was assembled 7-metres away from the face of the buildings to create large buttresses. Due to the scale of the buttresses, 18-tonne water containers were needed to weigh down the frame to stop lifting. Extensive Beam work was used to create the apex roofs while a mixture of tin and specially installed shrink wrap coverings were used to protect the buildings from adverse weather conditions.
Case Studies